Construction of Globe Life FIeld in Arlington, TZ is over 70 percent complete

Construction of Globe Life FIeld in Arlington, TZ is over 70 percent complete


[BLANK_AUDIO] Say, we’re more, little over 70% complete. We probably have 13 to 1400 men and
women on the job every day. And the work day sometimes will go almost
around the clock because particularly when we’re doing the precast work.>>Our plan is to have all
of the operable trusses, up in the air by the end of October. That’ll allow us to take, to dismantle,
the large frame that you see down there, and then start the main field activities.>>We’ve already announced
a March 23 against the Cardinals. We’ve announced a home opener
on March 31st againt the Angels. I would say the target they have a
countdown clock, the target is March one. [BLANK_AUDIO]